| Project Name: | Centaur Processing Building |
| Client: | U.S. Army Corps of Engineers |
| Location: | Cape Canaveral Air Force Station, Florida |
| Magnitude: | $34 Million |
|
 |
The project included the construction of a 116,400 sf multilevel rocket assembly facility, which featured a large multilevel Class 100,000 clean room, a 15 ton clean room compatible bridge crane, movable clean room compatible rocket assembly platforms, large vertical lift doors, a pile foundation, and utilities. The articulating platforms were mounted to fixed platforms to fully encircle the rockets creating 360 degree working platforms at various levels.
|
|
|
| ‹ Return to Completed Projects |
|
|
|