The project included the
resurfacing of 4.5 miles of existing roadway, reconstructing 1.5 miles
of Igloo access roads, constructing transporter turnarounds and loading
areas, widening a 2.5 mile road, and modifying the existing drainage
pipes all within an area of highly restricted access. Outside of the
restricted area, was the construction of additional roadways, a new
Sentry Station, and Site Security Control Center, complete with an
operating vehicle barrier to prevent unauthorized access. Two 100,000
pound electrical transformers, requiring rail car delivery due to their
size, were installed to provide adequate electric power to the Chemical
Stockpile Disposal Plant on the arsenal.