This
project consists of removal of the existing I-wall; construction of
approximately 4,950 feet of new T-wall; transition of the T-wall to the
existing levee on the east end and a portion of the levee to be
constructed in this project; construction of 2,120 feet of levee by
enlarging the existing levee, including slope pavement on the
floodside; construction of approximately 125 feet of new I-wall; and
flood protection improvements to the outfall of the St. Charles Pump
Station, including an automated sluice gate.